SECTION [Section number per office standard]
SMOKE-PROTECTIVE CURTAIN ASSEMBLIES — ELEVATOR HOISTWAY OPENINGS
PART 1 — GENERAL
1.1 SUMMARY
- Section includes: smoke-protective curtain assemblies at elevator hoistway door openings, as scheduled, including housings, guides, controls, power supplies and accessories required for a complete listed system.
- Related requirements: Division 14 elevators; Division 28 fire detection and alarm; Division 26 electrical; Division 09 ceilings and finishes.
1.2 REFERENCES
- International Building Code, 2024 edition, as adopted and amended by the authority having jurisdiction (AHJ). Compliance path: IBC 2024 Section 3006.3, item 5 (smoke-protective curtain assemblies for hoistways).
- UL 1784, Air Leakage Tests of Door Assemblies and Other Opening Protectives.
- UL 864, Control Units and Accessories for Fire Alarm Systems (control unit, where required by the listing).
- NFPA 105, Standard for Smoke Door Assemblies and Other Opening Protectives.
- NFPA 72, National Fire Alarm and Signaling Code (initiating devices and interface).
- ASME A17.1, Safety Code for Elevators and Escalators (coordination at hoistway entrances).
1.3 ACTION SUBMITTALS
- Product data for each assembly, including listing and test documentation for the complete assembly as installed.
- Shop drawings: opening schedule with clear dimensions; head, jamb and sill conditions; housing size and mounting; ceiling interface; wiring diagrams; sequence of operation.
- Listing or evaluation report identifying the assembly as a smoke-protective curtain assembly meeting Section 3006.3, item 5.
- Samples: curtain fabric and housing finish ([finish]).
1.4 INFORMATIONAL SUBMITTALS
- Installer qualifications: written authorization from the manufacturer.
- Field acceptance test reports.
- Operation and maintenance data, including periodic inspection and testing requirements.
1.5 QUALITY ASSURANCE
- Manufacturer: [__] years of experience producing listed smoke-protective curtain assemblies.
- Installer: trained and authorized by the manufacturer for the assemblies specified.
- Single source: provide all assemblies, controls and accessories from one manufacturer.
1.6 COORDINATION
- Elevator: coordinate housing location, guide attachment and clearances with the elevator contractor and hoistway entrance requirements.
- Fire alarm: coordinate initiating devices, monitoring and the deployment signal with Division 28.
- Electrical: coordinate dedicated power circuits and locations with Division 26.
- Ceilings: coordinate housing recess, access and finish with Division 09.
1.7 WARRANTY
- Manufacturer's warranty against defects in materials and workmanship: [__] years from substantial completion.
PART 2 — PRODUCTS
2.1 MANUFACTURERS
- Basis of design: [manufacturer and model].
- Acceptable manufacturers: [list, or 'subject to compliance with requirements'].
- Substitutions: in accordance with Division 01. Proposed substitutions must include listing and test documentation for the complete assembly.
2.2 PERFORMANCE REQUIREMENTS
- Assembly tested and labeled as a complete system in accordance with UL 1784, in the configuration installed.
- Automatic deployment upon a signal from the building fire alarm system or listed smoke detection, as required by the listing and the AHJ.
- Fail-safe deployment upon loss of power, as tested and listed.
- Standby power: integral battery or listed power supply sufficient for [__] hours, or as required by the listing.
- Controlled descent at the speed and with the safety features required by the listing.
- Means to test and reset the assembly without specialized tools, per the manufacturer.
2.3 COMPONENTS
- Curtain: smoke-resistant fabric as tested in the listed assembly.
- Housing: concealed head housing; finish: [finish].
- Side guides or edge retention: as tested in the listed assembly.
- Bottom bar: weighted, as tested in the listed assembly.
- Controls: control unit listed to UL 864 where required by the assembly listing; supervised interface with the fire alarm system.
PART 3 — EXECUTION
3.1 EXAMINATION
- Verify opening dimensions, head height, ceiling conditions and blocking before installation. Report conflicts in writing.
3.2 INSTALLATION
- Install in accordance with the manufacturer's instructions, the assembly listing and NFPA 105.
- Do not modify components or field conditions in a way that departs from the tested assembly.
3.3 FIELD QUALITY CONTROL
- Perform acceptance testing of each assembly in accordance with NFPA 105 and the manufacturer, in the presence of the AHJ where required.
- Test deployment from the fire alarm signal and on loss of power. Submit written test reports.
3.4 DEMONSTRATION
- Train the Owner's personnel in operation, testing, reset and periodic inspection. Provide [__] hours of on-site training.
3.5 MAINTENANCE
- Provide written requirements for periodic inspection and testing in accordance with NFPA 105 and the manufacturer.
END OF SECTION